Schedule network · Diagram Design

The parallel task has one day of float

An illustrative task plan. Follow precedence, then read the schedule in each box.

Illustrative five-task scheduleA branches into B and C, then joins at D before E. Finish is nine days; C has one day of float.PROJECT FINISH 9 daysA: ScopeDUR 2 daysES 0EF 2LS 0LF 2TF 0CRITICALB: BuildDUR 4 daysES 2EF 6LS 2LF 6TF 0CRITICALC: PrepareDUR 3 daysES 2EF 5LS 3LF 6TF 1FLOATD: IntegrateDUR 2 daysES 6EF 8LS 6LF 8TF 0CRITICALE: ReleaseDUR 1 daysES 8EF 9LS 8LF 9TF 0CRITICALILLUSTRATIVE SCHEDULE · days · ORIGIN 0 · FINISH-TO-START · ZERO LAGTask widths and spacing are not proportional to time.

Critical chain

A, B, D and E determine the nine-day finish.

One day of float

C can move from day 2 to day 3 without delaying D.

Boundary

Illustrative durations; no calendar or resource constraints.