Schedule network · Diagram Design
The parallel task has one day of float
An illustrative task plan. Follow precedence, then read the schedule in each box.
Critical chain
A, B, D and E determine the nine-day finish.
One day of float
C can move from day 2 to day 3 without delaying D.
Boundary
Illustrative durations; no calendar or resource constraints.